Tiling complete, garage door on, electrical started – Day 218 – March 30, 2018

Some more good progress the last couple of weeks.

  • Inside tiling has been completed
  • Vents fitted for Heating and Cooling
  • Garage door fitted
  • Electrical install started (just a couple of items remaining)
  • Formwork for remaining concrete done (driveway and alfresco)

A few days of inactivity with the Easter long weekend making for 2 short work weeks; Friday and Monday off.

What’s left? Not sure about the order in which these things will be carried out but these are the remaining things I can think of

  • Pour concrete for driveway, alfresco and outdoor shower
  • Tiling for outdoor shower
  • Install security system
  • Install remaining lights (garage facade and pendant bar over island bench)
  • Install ducted vacuum motor and outlets
  • Fit all plumbing fixtures; toilets, taps, basins
  • Timber capping on stairs
  • Install all kitchen appliances
  • Door furniture (handles/locks)
  • Install shelving for walk-in robes and pantry
  • Install stone benchtop in walk in pantry
  • Additional paint touch-ups
  • Installation of control panel and outside compressor for heating and cooling
  • Timber floor sanding and coating
  • Carpet laying
  • Any tidy-ups that come out of final walkthrough by us and the builder

When it’s all listed out there’s still plenty of work to be done. Hopefully it can be scheduled to run together closely.

The facade is now complete with garage door fitted.

Formwork in place for concrete to extend alfresco. This was overlooked during the initial slab pour back in September last year.

Vents and downlights installed in ceiling.

Lights fitted to bedrooms.

Ready for pouring the driveway concrete.