Paint Touch-ups, house cleaned, additional fittings – Day 250 – May 1, 2018

Another week  passes by and we inch closer to handover. As you’d expect, there’s lots of small changes, with no structural work going on. Our site supervisor has done his initial walkthrough and placed marking tape on the various elements that need filling, painting, cleaning, straightening and replacing. We’ve been given a tentative walkthrough date of May 8 (next Tuesday). Potential handover date – May 18/19.

Updates for the past week

  • Carpets installed
  • Outdoor shower installed
  • House cleaned
  • Additional plumbing fittings
  • Painting touch-ups

Work scheduled for this week

  • Plastering touch-ups
  • Painting touch-ups
  • Final clean

NBN fibre to the premises. Yeah!

Carpets in the office.

Polished floors, clean walls and shiny cupboards. Almost ready to move in.

All windows have been cleaned with dirty marks and manufacturer stickers removed.

Outdoor shower installed.