Exterior cladding update – Day 100 – December 1, 2017

The external cladding is almost complete with only a small section remaining on the eastern side of the house. This is due to a window needing to be replaced before cladding can be completed – wrong type of window with top of vanity running directly into window .

It was a good time to get the cladding installed with an inch of rain falling over the weekend.

Next week should see the completion of external cladding, rough-in of the heating/cooling system, install of insulation batts and perhaps a start on plastering.

The facade starting to take shape. Bricks around the garage will be rendered and paint applied to the cladding on the second storey. Will be good when the scaffolding finally comes down.

Shiplap cladding installed around the office and porch.

Lake Torquay in the back yard.

View of cladding from the rear.

View of cladding from the eastern side. Small section still incomplete.

View of cladding from western side.

Western side – where the cladding meets the bricks.