Driveway done, ready for plumbing – Day 226 – April 7, 2018

The entry to the house looks very different now with the aggregate concrete poured during the week. Additional concrete for the alfresco and the outdoor shower was also poured.

A huge week coming up with the following work planned.

  • Plumbing fit-off
  • Shower screen install
  • WIR shelving install
  • Driveway sealed
  • Carpenter fit-off
  • Final site clean

Our flooring guys will be onsite the following week to perform the floor sanding and sealing.

While there’s still plenty of small details to be sorted out we’ve been provided with an approximate handover date of May 9. Fingers crossed everything goes smoothly and we hit that date.

Concrete for the driveway and porch has been poured.

Riley giving the outdoor shower a test drive.

Additional concrete poured for the alfresco (missed when the slab was poured)

Flyscreens fitted to the sliding doors.

Plumbing hardware waiting to be fitted.

Basin fitted to downstairs powder room.

Tiling completed around ensuite vanity.

Tiling completed in enquite shower.

Tiling complete in main bathroom.

Tiling completed in upstairs powder room.

Front porch.