Tag Archive: Upstairs

Second floor windows – Day 74 – November 5, 2017

Things have slowed down with the next stage of construction waiting for scaffolding to be erected and tradespeople to become available.

This weeks inspection showed the following updates

  • Scaffolding erected on second storey
  • Plumbing installed between 2nd storey and ground floor
  • Windows installed on second storey

Next stage should see cladding installed on the second storey as we move towards the lock-up milestone.

See below for some recent photos, a walkthrough of the second storey and some drone footage showing the surrounding area.

Current view from the front. When the scaffolding comes down next time we’ll have a view much closer to the finished design.

Plumbers have been busy installing drainage for bathrooms and toilets upstairs.

Birds eye view of the house and surrounding blocks yet to be developed.

View from the western side.

View from the rear

A view of the house and surrounding area. Directly behind our block will be another row of houses, bordering the road currently being built. Further North is the wetland area and off in the distance you can sea the new Torquay Coast Primary School that the boys will attend.

View from the front with the wetland area in the background.

See below for a video showing the ongoing development and construction adjacent to our block.

See below for a video walkthrough of the second storey.