Walkthrough Day – Day 260

The site supervisor had already carried out his own review and the painters and plasterers had performed a series of touch-ups in preparation for our walkthrough. Overall the review went well, the house looks great and we can’t wait to move in.

However, between us and the builder we identified further areas that require additional touch-ups. For the most part, nothing too serious, just a bit of additional gap filling, sanding and painting required. On the larger scale the WIR cabinets in the master bedroom didn’t match the dimensions on the plan so they’ll need to be replaced and the extreme weather over the past few days uncovered a leak in some of the flashing that introduced an unplanned water feature in Riley’s bedroom.

So, instead of a weeks worth of finishing it’ll probably be closer to 2 weeks. That includes the install of kitchen appliances and some of the electrical fittings. So close, but not yet.

Rather than share some photos of the almost finished house I thought I’d post some photos of our current temporary accommodation. It’s more beach shack that beach house but we know it’s a temporary stop-over before we move into our dream home.

Not long now…

Modern stove and oven

Walk in pantry

The laundry

The main bathroom with step in shower/bath combo

Water saving showerhead

Hardcore door handles

Creative electrical work

Feature light in the lounge with timber lined walls and ceiling

 

Ready for plaster – Day 106 – December 7, 2017

Insulation has been installed in the walls and ceiling space and plaster has been delivered to site ready for the plasterers to start on Saturday

We carried out a walkthrough of the build to inspect the location of all electrical work prior to plastering commencing.

Nothing new from the outside

Plaster sheets ready to be hung.

Insulation batts installed throughout the house.

Vents for the heating and cooling system.

One last look at all the utilities before the plaster goes on.

Preparing for plaster – Day 86 – November 17, 2017

Plenty of activity onsite with progress marching towards the lock-up stage. Some wet weather during the week stopped cladding from commencing so we’re expecting that to start this coming Monday.

Progress for the week

  • Bath installed
  • Flashing applied to top of brickwork
  • Eaves installed
  • Cavity sliding door mechanism installed
  • Frame squared up in preparation for plaster
  • Metal rails fixed to ceiling in preparation for plaster
  • Various cladding materials delivered to site, ready for installation next week
  • More plumbing rough-in
  • A couple of temporary doors installed

Nothing much new to show from the front.

Double cavity sliding doors in the office.

Eaves installed around the entire home.

View down the hallway to the temporary front door.

Cladding to be used on the second storey has been delivered to site.

Metal rails have been fixed to the ceiling throughout the entire house. Plaster sheets will be fixed to these after the electrical rough-in has been completed.

Flashing has been applied to the top of the brickwork. This will provide a weatherproof seal between the top of the brickwork and the cladding on the second storey.

A pack of spotted gum boards. These will be fixed to the front of the house where there is no brickwork (around the office).