Tag Archive: Climate Control

Ready for plaster – Day 106 – December 7, 2017

Insulation has been installed in the walls and ceiling space and plaster has been delivered to site ready for the plasterers to start on Saturday

We carried out a walkthrough of the build to inspect the location of all electrical work prior to plastering commencing.

Nothing new from the outside

Plaster sheets ready to be hung.

Insulation batts installed throughout the house.

Vents for the heating and cooling system.

One last look at all the utilities before the plaster goes on.