Shower screens, mirrors and shelving all done – Day 239 – April 20, 2018

Another productive week with more boxes ticked off.

  • Lead-in connection for NBN installed
  • Shower screens
  • Bathroom mirrors
  • Shelving for robes

The floor sanders started on Friday and carpet install is booked in for next week so all floors will be covered by the end of the week. From there it’ll be time for the builder to organise final touch-ups in order to prepare for handover.

Almost there…

Shower screen in ensuite.

 

Sometimes it’s the little things, like door handles!

Timber capping on the raked wall for the stairs.

Timber handrail.

Glass sliding doors in the office.

Shower screen, mirror and plumbing fittings installed in the main bathroom.

Shelves and drawers in the master walk-in robe.

Vanity with wall-mounted tap in the ensuite.

Plumbing fixtures, door furniture and final fit out – Day 232 – April 13, 2018

After many months the temporary fence has finally been removed, providing a clear view of the house. As an added bonus the onsite porta-loo has also been removed providing our first photo of the house facade without a dunny in front!

Progress onsite this week

  • Water-proofing of outdoor shower
  • Commenced install of plumbing fixtures
  • Installed door furniture
  • Install of shelving
  • Install of data cabling and cabinet
  • Sealed the concrete driveway
  • A bit more upstairs that we couldn’t see

Plan for the week ahead

  • Tiling for outdoor shower
  • Timber floor sanding and coating

 

Front facade without the fence and toilet.

The kitchen sink now has a tap.

A view of cabinetry installed in the entry from the garage. Not sure why it’s there – we didn’t ask for it!?

Recycled water taps installed.

Data cabinet installed in the garage. Ready for NBN fibre to the premises – yeah!

 

Pendant light in the stairwell. A wooden UFO?

 

Almost looks ready to move in.

Driveway done, ready for plumbing – Day 226 – April 7, 2018

The entry to the house looks very different now with the aggregate concrete poured during the week. Additional concrete for the alfresco and the outdoor shower was also poured.

A huge week coming up with the following work planned.

  • Plumbing fit-off
  • Shower screen install
  • WIR shelving install
  • Driveway sealed
  • Carpenter fit-off
  • Final site clean

Our flooring guys will be onsite the following week to perform the floor sanding and sealing.

While there’s still plenty of small details to be sorted out we’ve been provided with an approximate handover date of May 9. Fingers crossed everything goes smoothly and we hit that date.

Concrete for the driveway and porch has been poured.

Riley giving the outdoor shower a test drive.

Additional concrete poured for the alfresco (missed when the slab was poured)

Flyscreens fitted to the sliding doors.

Plumbing hardware waiting to be fitted.

Basin fitted to downstairs powder room.

Tiling completed around ensuite vanity.

Tiling completed in enquite shower.

Tiling complete in main bathroom.

Tiling completed in upstairs powder room.

Front porch.